Our team will be working with the Georgia Department of Revenue, compliance division in order to develop an auditor Time Sheet/Inventory System. The system will provide two levels of security: Supervisor and Auditor. We will be providing Auditors with a PDA application that allows for the creation of time sheets and itineraries. The application will display a calendar itinerary to schedule appointments and audits. Then the application should take the scheduled information and create a time sheet based on the itinerary.
The client has asked that the:
- Application must be thoroughly documented
- Updated ERD Model
- Which file does what function
- Code must be commented
- Use functions and stored procedures whenever possible
- Adequate white space
- Variable names must be descriptive
- C# is preferred but any .NET language will suffice
The Database requirements are:
- SQL Server 2000 optimal
- Access is doable and we will convert to SQL
|
Henry Rutherford III
Compliance Division
Desk: (404) 417-6497
Pager: (404) 382-1137 |
| Dianna Knight |
Project Manager - Leader |
csu10679@ |
| John Shaffer |
Tester and Customer Liaison |
csu12748@ |
| Lester Henry |
Document Manager - Web Master |
csu15072@ |
| Tim Hare |
Developer |
csu15072@ |
|
| Resource |
When Needed |
Justification |
Number |
| Dreamweaver MX2004 |
Entire Semester |
Web Development |
2 |
| Palm OS Programming |
Entire Semester |
Aid with Programming |
1 |
| PalmOS |
Entire Semester |
PalmOS Testing Sync |
1 |
| PalmOS Test Suite |
Entire Semester |
Requirement for develop |
4 |
|
Task |
Who |
Time |
Notes |
| 1.0 Kick Off Meeting |
All Members |
30min |
Team Organizations |
| Contact Client/Research |
John |
5 hour |
Both groups were represented |
| Meeting With Client |
Tim/John/Lester |
1 hour |
Both groups were represented |
| Meeting: James Carrol |
Tim |
1 hour |
Programming for PalmOS |
| 2.2 Prepaire Work Breakdown |
Dianna/John |
2 hours |
first draft |
| 5.0 Web Site Development |
Dianna/Lester |
20 hours |
first draft |
| Research programming |
John/Tim |
60 hours |
PalmOS/Sync |
| 2.5 Project Plan |
Dianna |
4 hours |
first draft |
| 2.7 Requirements |
Dianna |
4 hours |
first draft |
|
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
30min |
Project Discussion |
| Research Sync |
John |
2 hour |
How to sync the PalmOS up |
| 2.3 Used Case Scenarios |
Lester |
3 hour |
development |
| 7.0 Testing research |
John |
6 hour |
White/Black box and implement |
| 2.2 Revise Work Breakdown |
Dianna/John |
2 hours |
second draft |
| 5.0 Web Site Development |
Dianna/Lester |
20 hours |
second draft |
| Research Programming |
John/Tim |
60 hours |
PalmOS/Sync |
| 2.5 Project Plan |
Dianna |
2 hours |
second draft |
| 2.7 Requirements |
Dianna |
2 hours |
second draft |
>>> |
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
30min |
Project Discussion |
| Programming Research |
John |
2 hour |
development |
| 2.3 Used Case Scenarios |
Lester |
4 hour |
use case model |
| 7.0 Testing research |
John |
6 hour |
White/Black box and implement |
| 2.2 Revise Work Breakdown |
Dianna/John |
2 hours |
added in expenses report |
| 5.0 Web Site Development |
Dianna/Lester |
10 hours |
updates |
| Research Programming |
John/Tim |
60 hours |
PalmOS/Sync |
| 2.5 Project Plan |
Dianna |
2 hours |
adding information |
| 2.7 Requirements |
Dianna |
2 hours |
second draft adding information |
| 2.4 Project Schedule |
Dianna |
2 hours |
Gant Chart and others |
| 2.6 Change Control |
Dianna/John/Lester |
2 hours |
Client added expenses report |
|
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
30 min |
Project Discussion |
| Work Breakdown Update |
John |
2 hour |
finalizing |
| 2.3 Used Case Scenarios |
Lester |
6 hour |
use case model |
| 7.0 Testing research |
John |
6 hour |
White/Black box and implement |
| 2.8 development Quality |
Dianna/John |
2 hours |
development paper work |
| 5.0 Web Site Development |
Dianna/Lester |
10 hours |
updates |
| Research Programming |
John/Tim |
60 hours |
PalmOS/Sync |
| 2.5 Project Plan |
Dianna |
2 hours |
adding information |
| 2.7 Requirements |
Dianna |
2 hours |
adding information |
| 2.4 Project Schedule |
Dianna |
2 hours |
Gant Chart and others updates |
|
Task |
Who |
Time |
Notes |
| Modeling |
John/Lester/Dianna |
2 hour |
Development |
| 2.3 Used Case Scenarios |
Dianna |
1 hour |
Finalizing use case model |
| Data Delivery/Interface |
John/Tim |
6 hour |
Finalizing Data Delivery and look |
| 2.8 development Quality |
Dianna/John |
2 hours |
development paper work |
| 5.0 Web Site Development |
Dianna/Lester |
1 hours |
updates |
| Research Programming |
John/Tim |
10 hours |
PalmOS/Sync |
| 2.5 Project Plan |
Dianna |
2 hours |
adding information |
| 2.7 Requirements |
Dianna/Lester |
2 hours |
adding information |
| 2.4 Project Schedule |
Dianna |
2 hours |
Gant Chart and others updates |
>>> |
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
1 hour each |
Project Discussion |
| Finish modeling |
John/Lester/Dianna |
2/1/1 hour(s) |
Model for the software development |
| 2.3 Redefine Case Scenarios |
Dianna |
1 hour |
Some changes were made after project was analyzed |
| 5.1 research into Hot Sync |
John/Tim |
2/2 hours |
After discover of data chooses of the system. |
| 2.4 Schedule Schedule |
Dianna/Lester |
1/1 hour |
Adjust schedule |
| 5.0 Web Site Development |
Dianna/Lester |
4/2 hours |
updates for Project Plan delivery |
| Research Programming |
John/Tim |
5/10 hours |
PalmOS/Sync |
| 2.4.5 Project Plan |
Dianna |
2 hours |
updating work breakdown, gant and other documents |
| 6.2 Develop Interface |
Tim |
2 hours |
Develop the first screen interface layout |
| 6.2 Develop Interface |
Lester |
3 hours |
develop the necessary bit map graphics for the application |
|
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
1 hour each |
Project Discussion |
| Meeting with James |
Tim |
1 hour |
Development Assistance |
| Documentation Development |
Dianna/Lester |
2/1 hour |
Weekly updates, update documents, and communication |
| 5.0 Web Site maintained |
Dianna/Lester |
2/1 hours |
updates |
| Install and short Intro to Palm Developer Suite |
All Members |
2 hours each |
Tim will instruct all members about the development suite |
| Develop Graphics |
Lester |
4 hours |
create symbols for the interface |
| 2.8 Quality Assurance Plan |
Lester |
4 hours |
create documentation |
| 2.9 Develop Testing Plan |
John |
8 hours |
determining all testing and create a plan |
| Communication |
John |
1 hours |
Communication with client and additional team |
| 6.2 Develop Initial Interface |
Tim/Dianna |
8/2 hours |
This is the entry screen for the project |
|
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
1 hour each |
Project Discussion |
| Meeting with James |
Tim |
1 hour |
Development Assistance |
| Documentation Development |
Dianna/Lester |
1/1 hour |
Weekly updates, update documents, and communication |
| 5.0 Web Site maintained |
Dianna/Lester |
1/1 hours |
updates |
| 2.9.1 Develop Testing Cases |
John |
8 hours |
Use white box testing working with Tim |
| 5.0 Web Site Development |
Dianna/Lester |
1/1 hours |
updates |
| 5.1 Develop Sync System |
Dianna |
8 hours |
PalmOS/Sync |
| 6.2 Develop Initial Interface |
Tim/Lester |
2/1 hours |
Polish |
| 6.4 Job Interface Screen |
Tim/Lester |
6/2 hours |
The user will determine what function to go to Add, Delete, update, create job info. |
| Communication |
John |
1 hours |
Communication with client and additional team |
| Build Tables Codes |
Lester/Tim |
7/1 hours |
Build the tables for the Job/Supervisor codes
|
>>> |
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
1 hour each |
Project Discussion |
| Meeting with James |
Tim |
1 hour |
Development Assistance |
| Documentation Development |
Dianna/Lester |
1/1 hour |
Weekly updates, update documents, and communication |
| 5.0 Web Site maintained |
Dianna/Lester |
1/1 hours |
updates |
| 2.91.1 Testing |
John |
8 hours |
test 6.2 Develop Initial Interface 6.4 Job Interface Screen |
| 5.0 Web Site Development |
Dianna/Lester |
1 hours |
updates |
| 5.3.1 Coding Sync |
Dianna |
8 hours |
PalmOS/Sync and the XML |
| 6.4 Job Interface Screen |
Tim/Lester |
2/1 hours |
Polish and finalize |
| 6.4.1 Add New Job Info |
Tim/Lester |
8/3 hours |
The user will determine what function to go to Add, Delete, update, create job info. |
| Communication |
John |
1 hours |
Communication with client, additional team and Jon |
|
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
1 hour each |
Project Discussion |
| Meeting with James |
Tim |
1 hour |
Development Assistance |
| Documentation Development |
Dianna/Lester |
1/1 hour |
Weekly updates, update documents, and communication |
| 5.0 Web Site maintained |
Dianna/Lester |
1/1 hours |
updates |
| 2.91.1 Testing |
John |
8 hours |
test 6.4 Job Interface Screen 6.4.1 Add New Job Info |
| 5.0 Web Site Development |
Dianna/Lester |
1 hours |
updates |
| 5.3.2 Incorporate Sync Coding |
Dianna |
8 hours |
PalmOS/Sync and the XML |
| 6.4.2 Edit Job Info |
Tim/Lester |
8/1 hours |
Edit information screen |
| 6.5 Query Time sheet Info |
Tim/Lester |
2/1 hours |
Start work on screen |
| Communication |
John |
1 hours |
Communication with client, additional team and Jon |
|
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
1 hour each |
Project Discussion |
| Meeting with James |
Tim |
1 hour |
Development Assistance |
| Documentation Development |
Dianna/Lester |
1/1 hour |
Weekly updates, update documents, and communication |
| 5.0 Web Site maintained |
Dianna/Lester |
1/1 hours |
updates |
| 2.91.1 Testing |
John |
8 hours |
test 6.4.2 Edit Job Info
6.5 Query Time sheet Info |
| 5.0 Web Site Development |
Dianna/Lester |
1/1 hours |
updates |
| 2.9.1.1 Testing |
Dianna/John |
8/.5 hours |
Black Box and White Box testing PalmOS/Sync and the XML |
| 6.5 Query Job Info |
Tim/Lester |
2/1 hours |
Polish and incorporate |
| 6.6 Edit Time sheet Info |
Tim/Lester |
8/3 hours |
Start development on Edit screen |
| Communication |
John |
1 hours |
Communication with client, additional team and Jon |
|
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
1 hour each |
Project Discussion |
| Meeting with James |
Tim |
1 hour |
Development Assistance |
| Documentation Development |
Dianna/Lester |
1/1 hour |
Weekly updates, update documents, and communication |
| 5.0 Web Site maintained |
Dianna/Lester |
1/1 hours |
updates |
| 2.91.1 Testing |
John |
8 hours |
test 6.5 Query Job Info
6.6 Edit Time sheet Info |
| 5.0 Web Site Development |
Dianna/Lester |
1/1 hours |
updates |
| 6.6.1.2 Enter Auditors Travel |
Tim/Lester/Dianna |
8/3/4 hours |
Develop forms (3 screen) |
| Prepare for Mid Demo |
All Members |
1 hour each |
Review all document and Prepare for presentation |
| Communication |
John |
1 hours |
Communication with client, additional team and Jon |
|
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
1 hour each |
Project Discussion |
| Meeting with James |
Tim |
1 hour |
Development Assistance |
| Documentation Development |
Dianna/Lester |
1/1 hour |
Weekly updates, update documents, and communication |
| 5.0 Web Site maintained |
Dianna/Lester |
1/1 hours |
updates |
| 2.91.1 Testing |
John |
8 hours |
test 6.6.1.2 Enter Auditors Travel |
| 5.0 Web Site Development |
Dianna/Lester |
1/1 hours |
updates |
| 6.6.1.2 Enter Auditors Travel |
Tim/Lester/Dianna |
2/2/4 hours |
Finish up and incorporate |
| 6.7 Query Time sheet Info |
Tim/Lester |
8/2 hours |
Start work on query screen |
| Communication |
John |
1 hours |
Communication with client,
additional team and Jon |
>>> |
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
1 hour each |
Project Discussion |
| Meeting with James |
Tim |
1 hour |
Development Assistance |
| Documentation Development |
Dianna/Lester |
1/1 hour |
Weekly updates, update documents, and communication |
| 5.0 Web Site maintained |
Dianna/Lester |
1/1 hours |
updates |
| 2.91.1 Testing |
John/Dianna |
2/2 hours |
test 6.6.1.2 Enter Auditors Travel 6.7 Query Time sheet Info |
| 2.9.3 Create Error reports |
John |
6 hours |
Prepare for Black Box testing |
| 5.0 Web Site Development |
Dianna/Lester |
1/1 hours |
updates |
| 7.3 Black Box Testing |
John/Dianna/Lester |
1/5/5 hours |
Test per test plan and report bugs |
| Bug Fixes |
Tim |
8 hours |
as bugs are discovered per testing they will be fixed |
| Communication |
John |
1 hours |
Communication with client, additional team and Jon |
|
Task |
Who |
Time |
Notes |
| 2.1 Weekly Meeting |
All Members |
1 hour each |
Project Discussion |
| Documentation Development |
Dianna/Lester |
1/1 hour |
Weekly updates, update documents, and communication |
| 5.0 Web Site maintained |
Dianna/Lester |
1/1 hours |
updates |
| 2.9.3 Error reports |
John |
10 hours |
Prepare all report for testing |
| 5.0 Web Site Development |
Dianna/Lester |
1 hours |
updates |
| Finalize all documentation |
Dianna/Lester |
10/8 hours |
Compile documentation and finalize all documents |
| Code Review |
Tim |
12 hours |
Review all code and add documentation |
| Communication |
John |
1 hours |
Communication with client, additional team, and Jon |
|
| |
1 |
2 |
3 |
4 |
5/6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
totals |
| Dianna Knight |
27 |
20 |
13.5 |
16.5 |
8 |
10 |
9 |
12 |
12 |
12 |
12 |
9 |
8 |
11 |
14 |
194.0 |
| John Shafer |
21 |
19 |
19.5 |
20 |
11 |
10 |
12 |
10 |
10 |
10 |
10.5 |
11 |
10 |
11 |
12 |
197.0 |
| Lester Henry |
5 |
9.5 |
10 |
11 |
5 |
8 |
13 |
14 |
8 |
8 |
8 |
8 |
8 |
9 |
12 |
136.5 |
| Tim Hare |
50 |
50 |
50 |
50 |
10 |
15 |
12 |
11 |
12 |
12 |
12 |
11 |
10 |
10 |
13 |
325.0 |
| Totals |
103 |
98.5 |
93 |
97.5 |
34 |
43 |
46 |
47 |
42 |
40 |
42.5 |
39 |
36 |
41 |
51 |
853.5 |
|
| |
1 |
2 |
3 |
4 |
5/6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
totals |
| Dianna Knight |
27 |
20 |
13.5 |
16.5 |
8 |
10 |
9 |
12 |
12 |
14 |
11 |
10 |
11.5 |
12 |
25 |
211.5 |
| John Shafer |
21 |
19 |
19.5 |
20 |
11 |
10 |
12 |
10 |
6 |
6 |
6 |
10 |
9 |
7 |
20 |
196.5 |
| Lester Henry |
5 |
9.5 |
10 |
11 |
5 |
8 |
13 |
14 |
5 |
5 |
6 |
6 |
5 |
4 |
20 |
126.5 |
| Tim Hare |
50 |
50 |
50 |
50 |
10 |
15 |
12 |
11 |
22 |
12 |
20 |
10 |
10 |
10 |
28 |
360.0 |
| Totals |
103 |
98.5 |
93 |
97.5 |
34 |
43 |
46 |
47 |
55 |
37 |
53 |
36 |
35.5 |
36 |
93 |
894.5 |
>>> |
| Risk |
Probability |
Impact |
Severity |
Contingency Plan |
| Inexperience with C and Palm Polite Programming |
6 |
10 |
60 |
The project is programmed in C/C++ for the palm poliet. The only person that can help when we hit a brick wall is a fellow student and becouse of this we run the risk of getting to a point that we as a team can not move forward. |
| Client Requirement Changes |
6 |
10 |
60 |
The schedule should be reviewed to see what would be effected and if change request is possible. The client should be aware if change is possible and what it would affect. See Instructor for guidance. |
| Loss of source code |
5 |
10 |
50 |
The developer will back-up all project source code once a day on a CD. It will be zipped and sent to the project manager for backup purposes. This is done in place of source safe. |
| Schedule Slips |
4 |
10 |
40 |
If due to added requirements by client. See Instructor for guidance. |
| Project Scope Unclear |
4 |
8 |
32 |
Being prepared at all meeting with client in order to ask questions and get clarification on items not clear. |
| Loss of Team Member |
3 |
10 |
30 |
Redistribute Duties to the remaining members. |
| Project Documentation Incomplete |
3 |
8 |
24 |
Redistribute when needed |
| Testing |
2 |
10 |
20 |
All members should be a part of testing |
| Project Understanding |
2 |
8 |
16 |
Research will be distributed to all members. However, when one member does not understand extra time should be applied to research. |
| Week Team Member |
2 |
7 |
14 |
Work should be reviewed and redistributed when necessary. (If the team member is putting fourth 100% effort) |
| Commitment To The Project |
3 |
4 |
12 |
- Meeting schedule should be firm
- All meeting will have an agenda
|
| Computer Crash |
1 |
9 |
9 |
All work should be mirrored by the designated backup team member |
|
Team GeorgiaPalm will be developing a PalmOS application that will facilitate Department of Revenue field agents in the efficient record keeping of their specific itinerary and time sheets. This GUI application will replace an archaic command line interface with a more intuitive user-friendly interface.
- The application will be written in C/C++ using the free Palm OS Developer Suite available at http://www.palmos.com/dev/dl/.
- The PDA application will need to synchronize with a desktop version.
- The customer will write the desktop version and all updating of the customers database will be handled between the desktop application and their database server.
- The PalmOS and the PocketPC version will have to deliver the PDA data to the desktop in a standardized file format.
- The desktop and PDA development teams will coordinate on the data file format.
- The PDA application will have multiple view options including day, week, and month.
- The auditors will input data through drop down list boxes and text input.
>>>
|
>>>
>>>
|
| * Estimated work day 4 hours |
| ID | Task Name |
Duration* |
Start | Finish | Resource Names | Complete |
| 1.0 |
Initiating | 2 days | Tue 1/18/05 | Wed 1/19/05 | Dianna Knight |
100% |
| 2.1 |
Project Meetings |
73 days |
Tue 1/18/05 |
Thu 4/28/05 |
Dianna Knight[5%],Lester Henry[5%],John Shaffer[5%],Tim Hare[5%] |
100% |
| 4.0 |
Web Interface Development | 8 days | Thu 1/20/05 | Mon 1/31/05 | Dianna Knight[40%],Lester Henry[20%] |
100% |
| |
Project Document Updates | 63 days |
Tue 2/1/05 |
Thu 4/28/05 |
Dianna Knight[30%],Lester Henry[30%],John Shaffer[10%],Tim Hare[10%] |
On Going |
| 2.2 |
Develop Work Breakdown | 2 days | Tue 1/25/05 | Wed 1/26/05 | Dianna Knight[30%] | 100% |
| 2.3 |
Create UseCases |
3 days |
Tue 1/27/05 |
Wed 1/30/05 |
Lester Henry |
100% |
| 2.3 |
Create Object Models |
14 days |
Tue 2/1/05 |
Wed 2/14/05 |
Lester Henry |
100% |
| |
Research |
14 days |
Tue 1/18/05 |
Wed 2/1/05 |
John Shaffer[50%], Tim Hare[50%] |
100% |
| 2.5 |
Prepare Project Plan | 10 days | Thu 2/10/05 | Wed 2/23/05 | Lester Henry[50%],Dianna Knight[50%] |
100% |
| 2.6 |
Prepaire Requirements Document |
10 days |
Thu 2/10/05 |
Wed 2/23/05 |
Lester Henry[50%],Dianna Knight[50%] |
95% |
| 2.8 |
Develop Quality Control |
7 days |
Tue 3/2/05 |
Wed 3/9/05 |
John Shaffer |
95% |
| 7.0 |
Whitebox Testing |
45 days |
Thu 2/10/05 |
Wed 4/13/05 |
John Shaffer[80%],Tim Hare[20%] |
95% |
| 3.0 |
Determine Data Delivery Structure | 8 days | Tue 2/1/05 | Thu 2/10/05 | Tim Hare[80%],John Shaffer[20%] |
80% |
| 5.0 |
Determine Type of Synchronization |
8 days |
Tue 2/1/05 |
Thu 2/10/05 |
Tim Hare[80%],John Shaffer[20%] |
80% |
| 3.3 |
Client Approval for Data Delivery System |
|
Thu 2/10/05 | Thu 2/10/05 |
Milestone |
|
| 6.2 |
Design Software Interface |
3 days |
Sun 2/20/05 |
Wed 2/23/05 |
Tim Hare[80%],John Shaffer[20%] |
90% |
| 6.2.2 |
Client Approval for Interface | |
|
Wed 2/25/05 |
Milestone |
|
| 5.0 |
Develop Sync System |
10 days |
Fri 3/9/05 |
Tue 3/18/05 |
Dianna Knight [80%],John Shaffer[20%] |
90% |
| 5.3.3 |
Test Hot Sync |
7 days |
Wed 3/19/05 |
Tue 3/26/05 |
Dianna Knight [80%],Lester Henry[20%] |
90% |
| 6.2 |
Develop Software Interface |
12 days |
Fri 2/25/05 |
Tue 3/8/05 |
Tim Hare[80%],Dianna Knight[20%] |
50% |
| |
Build Supervisor/Job Code Selection |
7 days |
Wed 3/2/05 |
Tue 3/8/05 |
Lester Henry [10%],Tim Hare[20%] |
50% |
| 6.4 |
Job Information Screen |
7 days |
Wed 3/9/05 |
Sat 3/15/05 |
Tim Hare[80%],Lester Henry[20%] |
50% |
| 6.4.1 |
Add New Job Info. |
5 days |
Wed 3/16/05 |
Sat 3/20/05 |
Tim Hare[80%],Lester Henry[20%] |
30% |
| 6.4.2 |
Edit Job Information |
5 days |
Wed 3/21/05 |
Sat 3/25/05 |
Tim Hare[80%],Lester Henry[20%] |
30% |
| 6.5 |
Query Time sheet Info |
5 days |
Wed 3/26/05 |
Sat 3/30/05 |
Tim Hare[80%],Dianna Knight[20%] |
30% |
| 6.6 |
Edit Time sheet Info |
5 days |
Wed 3/31/05 |
Sat 4/4/05 |
Tim Hare[80%],Lester Henry[20%] |
30% |
| |
First Demo |
|
Tue 4/5/05 |
Thu 4/7/05 |
Milestone |
|
| 6.6.1.2 |
Enter Auditors Travel |
5 days |
Mon 4/5/05 |
Sun 4/9/05 |
Tim Hare[80%],Dianna Knight[20%] |
30% |
| 6.7 |
Query Time sheet Info. |
5 days |
Mon 4/10/05 |
Sun 4/15/05 |
Tim Hare[80%],Lester Henry[20%] |
30% |
| 7.3 |
Blackbox Testing |
7 days |
Mon 4/18/05 |
Wed 4/24/05 |
Dianna Knight[40%],Lester Henry[40%],John Shaffer[20%] |
20% |
| |
Program Delivery | |
Mon 5/2/05 | Mon 5/2/05 |
Milestone |
|
| |
Project Presentation |
|
Tue 5/3/05 |
Tue 5/3/05 |
Milestone |
|
|
| * Estimated work day 4 hours |
| >>> |